Rising above London Bridge Station:
From Wiki:
The concrete core has now topped out at level 72, standing at 245 metres (804 ft).
The early part of January 2011 saw the installation of hydraulic screens. These are used to form the concrete floors that are needed for the hotel and apartment section of the tower. These will rise with the floors up to level 69. On 25 January 2011 the concrete pumps began pouring the first concrete floor at level 41.
By the end of February 2011 the concrete floors had risen to level 46 with a floor being poured on average every week. The cladding has also progressed mainly on the towers "backpack" where much of its 15 levels were cladded in a month, the cladding on the main tower though had slowed due to the concrete floors being poured above.
April 2011 saw steady progress in construction and cladding had enveloped half the buildings exterior . Pouring of the concrete floors had reached level 50 and progression on the towers cladding had picked up pace once again with cladding reaching level 38.


Leave a reply to Brian Micklethwait Cancel reply